New Pointe du Chéry Chairlift: Major Mont-Chéry Upgrade in Les Gets
Les Gets is continuing the modernisation of the Mont-Chéry ski area with the arrival of a new six-seater detachable chairlift at Pointe du Chéry. The new Pointe du Chéry chairlift will reuse, overhaul and recondition the existing Grains d’Or chairlift before relocating it to a new position on Mont-Chéry.
Rather than installing a completely new lift, the project takes a different approach by giving an existing lift a new lease of life. The Grains d’Or chairlift will undergo a comprehensive inspection, refurbishment and upgrade before being reinstalled on the upper section of Mont-Chéry.
The project is designed to improve ski lift capacity, comfort and access for skiers, while taking a more considered approach to investment and the renewal of existing ski area infrastructure.
Pointe du Chéry Chairlift: Project at a Glance
6 seats – Detachable chairlift
988m – Horizontal length
293m – Vertical elevation
2,000 skiers per hour – Capacity
5m/s – Maximum operating speed
POMA – Lift manufacturer
Modernising Mont-Chéry and Improving the Ski Experience
The Mont-Chéry sector of Les Gets ski area is currently equipped exclusively with fixed-grip lifts. The new six-seater detachable chairlift will significantly improve the efficiency and comfort of the lift system, with faster loading and reduced journey times. The detachable technology will also make boarding easier, helping to improve accessibility for a wider range of skiers, including families and less experienced skiers. The new chairlift will be located on the upper section of Mont-Chéry, connecting the current departure point of the Grande Ourse chairlift with the existing arrival point of the Pointe drag lift. With an operating speed of up to 5 metres per second and easier loading thanks to its detachable technology, the new Pointe du Chéry lift is expected to improve the overall skiing experience and the quality of the lift network on Mont-Chéry.
Why Is Les Gets Reusing an Existing Chairlift?
One of the most interesting aspects of the new Pointe du Chéry project is that the chairlift is not entirely new. Instead, Les Gets is reusing the existing Grains d’Or chairlift, extending the useful life of an existing piece of ski lift infrastructure while adapting it to meet the needs of the Mont-Chéry sector. The Grains d’Or chairlift is already well known to the technical teams, and its characteristics are considered suitable for its new location on Mont-Chéry. Reusing the lift also means that many of its existing components can be retained, reducing the need to manufacture an entirely new lift system. The approach is intended to make more efficient use of existing resources while helping to control the investment required to modernise the sector.
However, reusing the Grains d’Or chairlift does not simply mean moving it from one location to another. Before being brought back into service, the lift will undergo a complete inspection and overhaul of its safety-critical components, together with upgrades to its equipment. The project will also include measures to optimise electricity consumption. The new Pointe du Chéry chairlift therefore represents a different approach to modernising ski area infrastructure: reuse, refurbish and adapt an existing lift rather than automatically replacing it with an entirely new installation.
August 2026 – Preparing the Site
The first phase of the project has involved dismantling the existing lifts and preparing the locations for the new chairlift infrastructure. The Pointe drag lift has been dismantled, along with the Grande Ourse chairlift, clearing the way for construction of the future stations. At the top of Mont-Chéry, earthworks have also begun for the future upper station of the Pointe du Chéry chairlift. The first concrete foundations for the new station have now been poured, marking an important stage in the construction work. Meanwhile, work has also begun on dismantling the Grains d’Or chairlift, which is being prepared for its second life on Mont-Chéry. The components are being progressively removed and sent for detailed inspection as part of the refurbishment and reconditioning process. Once this work is complete, the lift will be transported and reinstalled on the upper section of Mont-Chéry.
August 2026 – Construction of the New Lift Infrastructure
Following the initial site preparation and dismantling work, the project has now moved into the next phase, with construction of the infrastructure for the future Pointe du Chéry chairlift. At the summit of Mont-Chéry, the first foundations for the upper station are taking shape. Work is continuing along the upper section of the lift line, with concrete foundations being constructed for the future lift towers.
Grains d’Or Chairlift Transported by Helicopter
The reuse of the Grains d’Or chairlift has also involved some impressive mountain logistics. The eight tower heads from the Grains d’Or chairlift were transported by helicopter to Mont-Chéry, where they will be reused as part of the new Pointe du Chéry lift line. The operation was carried out by Blugeon Hélicoptères using a Super Puma helicopter, an aircraft designed for lifting and transporting heavy loads in mountainous terrain, with a lifting capacity of up to four tonnes. The components were transported directly from the Grains d’Or sector to Mont-Chéry. They will now be prepared before being assembled along the future Pointe du Chéry chairlift line.
What Will the New Pointe du Chéry Chairlift Mean for Skiers?
Once operational, the new lift will replace the existing Pointe drag lift and provide a faster, more comfortable way to access the upper part of Mont-Chéry. The combination of six-seater detachable technology, a 2,000-person-per-hour capacity and a maximum speed of 5m/s will improve the movement of skiers through this section of the Les Gets ski area. For visitors skiing Mont-Chéry, the new lift will also mean easier loading and a more modern lift experience, while the reuse of the Grains d’Or chairlift gives an existing piece of ski infrastructure a new role. The construction work will continue over the coming months as the new Pointe du Chéry chairlift takes shape ahead of its planned opening.